House Construction Cost Calculator

Estimate the cost to build a house from the covered area, grey structure rate and finishing level, using 2026 Lahore rates you can edit. Updated: 12 October 2026

sq ft
All floors. A 5 Marla double-storey is about 2,250 sq ft.
Rs/sq ft
%

Estimated construction cost

Rs 17,572,500

2,250 sq ft covered · Standard (A-grade) finishing · Rs 7,810 per sq ft

Grey structure (Rs 3,100/sq ft)Rs 6,975,000
Finishing (Rs 4,000/sq ft)Rs 9,000,000
ContingencyRs 1,597,500
Total estimateRs 17,572,500

Get quotes from builders

Planning to build? Share a few details and up to 3 reliable contractors near you will contact you with a quote. Free, with no obligation.

Estimated cost by house size

Double-storey houses, grey structure at Rs 3,100/sq ft, with 10% contingency.

HouseCovered areaGrey structure onlyStandard finishing
5 Marla2,250 sq ftRs 7,672,500Rs 17,572,500
10 Marla4,500 sq ftRs 15,345,000Rs 35,145,000
1 Kanal7,500 sq ftRs 25,575,000Rs 58,575,000

How the estimate is calculated

  1. Grey structure = covered area × grey rate.
  2. Finishing = covered area × finishing rate for the level you pick.
  3. Contingency = a percentage of both, for price changes and extras.

These are planning figures. Get itemised quotes from two or three contractors based on your approved drawings before you start.

Frequently asked questions

What is the construction cost per square foot in Lahore in 2026?

Builders quote roughly Rs 2,800 to Rs 3,500 per sq ft for grey structure, and Rs 4,000 to Rs 6,000 more per sq ft for good (A-grade) finishing. Total cost for a standard house is about Rs 6,500 to Rs 9,000 per sq ft. Rates vary by area, design and materials.

What is the covered area of a 5 Marla house?

A double-storey 5 Marla house (1,125 sq ft plot at 225 sq ft per Marla) usually has 2,000 to 2,300 sq ft of covered area, depending on society bylaws for setbacks.

What does grey structure include?

Foundations, RCC frame and roof, brickwork, plaster, and basic electrical and plumbing pipes, without tiles, paint, wood, fittings or fixtures.

Why add a contingency?

Material prices (steel, cement, bricks) change during construction, and design changes are common. Keeping 10% to 15% extra helps you avoid stopping work midway.

Is this cost with or without the plot?

Without the plot. It also does not include architect fees, approval and map fees, or utility connections.